Projects

Print

SHPP Hodonín

Location: South of Hodonín, Czech Republic, on the river Morava

Current status: in full operation

Total installed capacity: 2,3  MW (2x1.15 MW)

Type of turbines: 2 x Kaplan vertical-axis turbines

Power generation in 2007: 7,645,580 kWh

 

 

SHPP Chynoriansky Mlyn

Location: South of Chynorany, Slovakia, on the river Nitra

Current status: in full operation

Total installed capacity: 2x 200 kW

Type of turbines: 2 x Kaplan horizontal-axis turbines

Planned power generation: 1,515,000 kWh

 